CBAP · Question #508
A business analyst (BA) asks participants in a workshop to write down their ideas about the feature being built on sticky notes place them on the wan and then group the ideas into similar themes…
The correct answer is B. prepare for requirements elicitation. The described technique - generating ideas on sticky notes and clustering them into themes - is affinity mapping, a collaborative exercise used to organize information and identify focus areas before formal requirements elicitation begins.
Question
A business analyst (BA) asks participants in a workshop to write down their ideas about the feature being built on sticky notes place them on the wan and then group the ideas into similar themes. The BA is using, this technique to:
Options
- Aprioritize requirements.
- Bprepare for requirements elicitation.
- Cidentify organizational capabilities.
- Dmanage stakeholder collaboration.
How the community answered
(22 responses)- A5% (1)
- B82% (18)
- C5% (1)
- D9% (2)
Why each option
The described technique - generating ideas on sticky notes and clustering them into themes - is affinity mapping, a collaborative exercise used to organize information and identify focus areas before formal requirements elicitation begins.
Prioritizing requirements involves scoring or ranking an existing set of requirements against defined criteria such as business value or risk, which is a different activity from clustering brainstormed ideas into themes.
Affinity mapping is a structured technique where participants externalize ideas on sticky notes and cluster them into related themes, revealing the key topic areas and knowledge gaps that should be addressed in subsequent elicitation sessions. By surfacing common concerns and grouping them before formal elicitation begins, the BA can design more targeted and comprehensive workshops. This preparation step ensures that elicitation activities are focused and that no significant topic area is overlooked.
Identifying organizational capabilities requires a structured assessment of existing business competencies, processes, and resources - not a free-form idea-generation and grouping exercise.
Managing stakeholder collaboration is an ongoing BA responsibility involving communication and engagement planning, not a specific outcome produced by grouping sticky-note ideas into themes.
Concept tested: Affinity mapping as elicitation preparation technique
Topics
Community Discussion
No community discussion yet for this question.