CBAP · Question #369
Contracts are currently managed by more than 20 contract owners across the organization, each happily managing in their own way. A business analyst (BA) is tasked to elicit requirements for…
The correct answer is B. Identify future state conditions. Before eliciting requirements for centralized contract management, the BA must first identify future state conditions to establish the desired end state that requirements will need to support.
Question
Contracts are currently managed by more than 20 contract owners across the organization, each happily managing in their own way. A business analyst (BA) is tasked to elicit requirements for centrally managing software maintenance and license contracts. Which of the following does the BA need to carry out first?
Options
- AIdentify business requirements
- BIdentify future state conditions
- CRecommend an off the shelf product
- DComplete an enterprise readiness assessment
How the community answered
(23 responses)- A4% (1)
- B78% (18)
- C4% (1)
- D13% (3)
Why each option
Before eliciting requirements for centralized contract management, the BA must first identify future state conditions to establish the desired end state that requirements will need to support.
Identifying business requirements is a subsequent step that depends on first understanding the future state - requirements describe what is needed to achieve that state, so they cannot be the starting point.
Identifying future state conditions is the correct first step because it defines the desired outcome and target operating environment that all subsequent requirements must achieve. Without a clear picture of how centralized contract management should function, the BA cannot meaningfully scope, elicit, or validate the business requirements that follow.
Recommending an off-the-shelf product is a solution recommendation that is premature before requirements are defined and analyzed.
An enterprise readiness assessment evaluates the organization's capacity to absorb change and is relevant later in the process, after the future state and requirements are understood.
Concept tested: Future state definition before requirements elicitation
Source: https://www.iiba.org/standards-and-resources/babok/
Topics
Community Discussion
No community discussion yet for this question.