A software company has won a contract to implement its product for a client. As part of the implementation work, a business analyst (BA) is asked to elicit information about the other client…

The correct answer is C. Activity. Sequence diagrams used to specify and model requirements to show how processes operate and interact with one another, and in what order.

Requirements Analysis and Design Definition

Question

A software company has won a contract to implement its product for a client. As part of the implementation work, a business analyst (BA) is asked to elicit information about the other client applications that will interface with the new system and provide the information graphically. The technical staff needs to understand the message interaction within the systems for key business transactions. Which type of diagram should the BA use?

Options

  • AProcess
  • BSequence
  • CActivity
  • DContext

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    7% (2)
  • C
    78% (21)
  • D
    4% (1)

Explanation

Sequence diagrams used to specify and model requirements to show how processes operate and interact with one another, and in what order.

Topics

#UML diagrams#activity diagram#system interfaces#elicitation modeling