Question

Henry is the business analyst for his organization. Management has created a pre-determined budget of $450,000 for his solution. Henry has identified the project requirements but now wants to prioritize them based on timeboxing and budgeting. Henry examines the cost of the requirements and begins removing the requirements from the allowed list in order to meet the $450,000 budget. What timeboxing or budgeting approach is Henry using?

Options

  • AParametric
  • BAll in
  • CSelective
  • DAll out

Unlock CBAP to see the answer

You've previewed enough free CBAP questions. Unlock CBAP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full CBAP Practice
Henry is the business analyst for his organization. Management has... | CBAP Q#26 Answer | NerdExam