CBAP · Question #248
You are the business analyst for your organization and are working with Sally, a project manager, for your organization. You and Sally are determining the cost of the labor, materials, equipment…
The correct answer is C. Rough order of magnitude cost estimating. Estimating the cost of labor, materials, equipment, and facilities for proposed solution alternatives is the process known as Rough Order of Magnitude (ROM) cost estimating.
Question
You are the business analyst for your organization and are working with Sally, a project manager, for your organization. You and Sally are determining the cost of the labor, materials, equipment, and facilities in order to achieve the different solutions that have been proposed for an identified problem. What is this process called?
Options
- ACost budgeting
- BExpert judgment
- CRough order of magnitude cost estimating
- DScoping the project costs
How the community answered
(49 responses)- A8% (4)
- B2% (1)
- C84% (41)
- D6% (3)
Why each option
Estimating the cost of labor, materials, equipment, and facilities for proposed solution alternatives is the process known as Rough Order of Magnitude (ROM) cost estimating.
Cost budgeting is the formal process of aggregating approved estimates into an authorized cost baseline - it follows estimation and does not describe the act of calculating initial solution costs.
Expert judgment is a technique applied during estimation activities, not a process for systematically calculating costs across labor, materials, equipment, and facilities.
Rough Order of Magnitude cost estimating produces high-level, approximate cost figures for proposed solutions during early project phases before detailed planning is complete. It explicitly accounts for the key cost categories - labor, materials, equipment, and facilities - to give decision-makers a comparative view of what each solution option would require financially. ROM estimates are used to support go/no-go decisions and solution selection, not to produce a formal budget baseline.
Scoping the project costs is not a recognized formal process in any standard business analysis or project management framework and does not describe structured solution cost estimation.
Concept tested: Rough Order of Magnitude cost estimating for solution alternatives