CBAP · Question #247
Management would like you to front-load the requirements with the most risk requirements. Why would management prefer the risky requirements first in the prioritization?
The correct answer is A. So if the risk comes true the project will fail will little investment in the work.. Front-loading risky requirements ensures that if a risk materializes and forces project failure, the organization has committed the minimum possible investment before discovering the problem.
Question
Management would like you to front-load the requirements with the most risk requirements. Why would management prefer the risky requirements first in the prioritization?
Options
- ASo if the risk comes true the project will fail will little investment in the work.
- BSo if the risk comes true then the project manager can mitigate the risk event.
- CSo if the risk comes true they'll receive the reward as soon as possible.
- DSo if the risk comes true then there's ample time to correct the problem.
How the community answered
(28 responses)- A79% (22)
- B11% (3)
- C7% (2)
- D4% (1)
Why each option
Front-loading risky requirements ensures that if a risk materializes and forces project failure, the organization has committed the minimum possible investment before discovering the problem.
Prioritizing high-risk requirements early exposes potential project-ending failures at the point of least financial and resource commitment. If a risk event proves a requirement infeasible or causes the project to fail, the organization avoids sinking the full project budget into a doomed effort. This is a deliberate 'fail fast and cheap' strategy that protects the organization from large sunk costs on undeliverable work.
The project manager's ability to mitigate a risk event is independent of when risky requirements are scheduled - front-loading changes the timing of exposure, not the PM's risk response capacity.
Risky requirements represent threats, not opportunities - there is no reward to receive sooner, and front-loading is not motivated by benefit realization.
Having ample time to correct a problem is a rationale for early risk detection generally, but the specific driver here is minimizing sunk cost when the risk is fatal, not enabling correction.
Concept tested: Risk-based requirements prioritization to minimize investment loss
Topics
Community Discussion
No community discussion yet for this question.