Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?

The correct answer is A. Scope verification. Scope Verification is the formal process performed at the end of each project phase to confirm deliverable completeness and secure customer sign-off before the project advances.

Requirements Life Cycle Management

Question

Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?

Options

  • AScope verification
  • BInspection of key results
  • CQuality control
  • DPhase gate review

How the community answered

(53 responses)
  • A
    75% (40)
  • B
    15% (8)
  • C
    6% (3)
  • D
    4% (2)

Why each option

Scope Verification is the formal process performed at the end of each project phase to confirm deliverable completeness and secure customer sign-off before the project advances.

AScope verificationCorrect

Scope Verification (called Validate Scope in PMBOK 5+) is the process of formalizing acceptance of completed project deliverables by the customer or sponsor. It is performed at the end of each project phase to confirm that all work meets the defined scope requirements and to obtain the formal authorization needed to proceed to the next phase.

BInspection of key results

Inspection of key results is a tool or technique applied within quality control, not a standalone formal process that governs phase completion and secures customer acceptance.

CQuality control

Quality control focuses on monitoring outputs against quality standards to identify defects, but it does not involve formal customer acceptance of deliverables as a gate for moving forward.

DPhase gate review

A phase gate review is a governance decision checkpoint evaluating whether the project should continue, change, or stop - it is not the dedicated process for verifying scope completeness and obtaining customer acceptance.

Concept tested: Validate Scope process at project phase end

Source: https://www.pmi.org/pmbok-guide-standards

Topics

#scope verification#phase gate review#customer acceptance#project phase

Community Discussion

No community discussion yet for this question.

Full CBAP Practice