CBAP · Question #170
Which of the following is the comparison of planned project results with actual project results?
The correct answer is A. Variance analysis. Variance analysis is the project control technique that compares planned baseline values against actual performance results to identify and quantify deviations.
Question
Which of the following is the comparison of planned project results with actual project results?
Options
- AVariance analysis
- BCost-benefit analysis
- CStatistical Sampling
- DTrend analysis
How the community answered
(28 responses)- A71% (20)
- B18% (5)
- C7% (2)
- D4% (1)
Why each option
Variance analysis is the project control technique that compares planned baseline values against actual performance results to identify and quantify deviations.
Variance analysis measures the difference between planned and actual project performance across scope, schedule, and cost dimensions. In Earned Value Management it produces metrics such as Schedule Variance (SV = EV - PV) and Cost Variance (CV = EV - AC), giving project managers the data needed to determine corrective actions when performance deviates from the plan.
Cost-benefit analysis weighs the total expected costs of a decision against its projected benefits to justify investment, and does not compare planned project results to actual results.
Statistical sampling selects a representative subset of a population for inspection as a quality technique, and is not used to compare planned versus actual performance.
Trend analysis examines historical performance data to forecast future project outcomes, making it forward-looking rather than a direct comparison of planned versus actual results.
Concept tested: Variance analysis for project performance measurement
Source: https://www.pmi.org/pmbok-guide-standards
Topics
Community Discussion