C_TSCM42_65 · Question #127
Which of the following consequences result when a production order is set to Technically Complete (TECO)? (Choose three)
The correct answer is B. Reservations are no longer relevant for material requirements planning. D. Capacity requirements are set to null. E. The order is no longer relevant for material requirements planning. See the full explanation below for the reasoning.
Question
Which of the following consequences result when a production order is set to Technically Complete (TECO)? (Choose three)
Options
- AConfirmations are no longer permitted.
- BReservations are no longer relevant for material requirements planning.
- CThe order and its operations receive the system status Locked (LKD).
- DCapacity requirements are set to null.
- EThe order is no longer relevant for material requirements planning.