Which of the following requirements is supported by using process orders?
The correct answer is D. Documentation of the production using an electronic batch record. See the full explanation below for the reasoning.
Question
Which of the following requirements is supported by using process orders?
Options
- ALinkage of documents to orders
- BUse of reference operation sets
- CUse of production/resource tools
- DDocumentation of the production using an electronic batch record
How the community answered
(31 responses)- A3% (1)
- B3% (1)
- C10% (3)
- D84% (26)