C_TSCM42_65 · Question #125

You want to produce a finished product only when it is requested by a customer order in make-to- order production. However, all assemblies need to be procured beforehand. How can you fulfill these…

The correct answer is C. Use strategy 50 (planning without final assembly) for the finished product and no strategy for all D. Use strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the. See the full explanation below for the reasoning.

Question

You want to produce a finished product only when it is requested by a customer order in make-to- order production. However, all assemblies need to be procured beforehand. How can you fulfill these requirements in SAP ECC? (Choose two)

Options

  • AUse strategy 30 (production by lots) for the finished product and strategy 70 (planning at the assembly
  • BUse strategy 40 (planning with final assembly) for the finished product and strategy 70 (planning at the
  • CUse strategy 50 (planning without final assembly) for the finished product and no strategy for all
  • DUse strategy 20 (make-to-order production) for the finished product and strategy 70 (planning at the

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    8% (2)
  • C
    80% (20)

Community Discussion

No community discussion yet for this question.