What master data do you need for material replenishment using the KANBAN procedure? (Choose two)
The correct answer is A. Production supply area E. Control cycle. See the full explanation below for the reasoning.
Question
What master data do you need for material replenishment using the KANBAN procedure? (Choose two)
Options
- AProduction supply area
- BProduct cost collector
- CRate routing
- DProduction version
- EControl cycle
How the community answered
(59 responses)- A75% (44)
- B7% (4)
- C3% (2)
- D15% (9)