Your company procures some materials exclusively through consignment, and you want the requirements planning for these materials to generate purchase requisitions for supplier consignment rather…

The correct answer is C. You must store an order book with at least one source of supply in the material master. D. You have to store a special procurement type and special procurement key for consignment in the. To trigger consignment purchase requisitions from MRP, two things must be in place in the material master. Option D is correct because the MRP 2 view must have the special procurement type set to external procurement and the special procurement key set to the consignment…

Consumption-Based Planning

Question

Your company procures some materials exclusively through consignment, and you want the requirements planning for these materials to generate purchase requisitions for supplier consignment rather than regular purchase requisitions. What do you have to do for each of the materials in question to make this work? There are 2 correct answers to this question.

Options

  • AYou have to store a default storage location for external procurement in the material master.
  • BYou have to store a special planning group for consignment in the material master.
  • CYou must store an order book with at least one source of supply in the material master.
  • DYou have to store a special procurement type and special procurement key for consignment in the

How the community answered

(60 responses)
  • A
    12% (7)
  • B
    5% (3)
  • C
    83% (50)

Explanation

To trigger consignment purchase requisitions from MRP, two things must be in place in the material master. Option D is correct because the MRP 2 view must have the special procurement type set to external procurement and the special procurement key set to the consignment indicator (e.g., "K"), which signals MRP to generate consignment requisitions instead of standard ones. Option C is correct because a source list (order book) entry must exist with at least one consignment info record as the source of supply - without this, MRP has no valid consignment source to reference when creating the requisition.

Option A is wrong because the default storage location for external procurement controls where goods are placed upon receipt, not what type of procurement requisition is generated. Option B is wrong because there is no such thing as a "special planning group for consignment" in SAP - planning groups are used to segment MRP runs, not to define procurement categories.

Memory tip: Think "Source + Special" - you need a Source list pointing to a consignment record (C) and a Special procurement key set to consignment in the material master (D). Both must point in the same direction for MRP to "see" consignment as the intended procurement path.

Topics

#consignment#special procurement key#MRP#purchase requisition