Confirmed quantities and dates must be recorded in the purchase order item. Your purchasing department expects suppliers to send purchase order confirmations and shipping notifications. What do you…

The correct answer is C. A confirmation control key with a sequence of two confirmation types. Option C is correct because the scenario demands two distinct supplier communications - an order acknowledgment and a shipping notification - which requires configuring a confirmation control key that contains a sequence of two confirmation types (e.g., order acknowledgment AB…

Configuration of Purchasing

Question

Confirmed quantities and dates must be recorded in the purchase order item. Your purchasing department expects suppliers to send purchase order confirmations and shipping notifications. What do you need to configure in Customizing? Please choose the correct answer.

Options

  • AA confirmation control key with at least one confirmation type marked as relevant for planning
  • BA confirmation control key relevant for the proof of delivery
  • CA confirmation control key with a sequence of two confirmation types
  • DA purchasing value key with the order acknowledgment indicator preset

How the community answered

(17 responses)
  • A
    6% (1)
  • C
    76% (13)
  • D
    18% (3)

Explanation

Option C is correct because the scenario demands two distinct supplier communications - an order acknowledgment and a shipping notification - which requires configuring a confirmation control key that contains a sequence of two confirmation types (e.g., order acknowledgment AB followed by shipping notification LA). The sequence ensures SAP expects both confirmations in order, and the confirmed quantities/dates from each are stored on the PO item as required.

Why the distractors fail:

  • A is partially right in concept but wrong in focus - "relevant for planning" is an attribute of a confirmation type that feeds confirmed data into MRP, but a single type only covers one confirmation, not both requirements.
  • B confuses the scenario with proof of delivery (POD), which is a GR-related process for verifying receipt, not a vendor confirmation/shipping notification workflow.
  • D misdirects to the purchasing value key, which governs tolerances and reminder intervals - the order acknowledgment indicator there only triggers reminder messages to vendors, not the structured confirmation tracking needed here.

Memory tip: Count the supplier messages. One message = one confirmation type; two messages (confirmation + shipping notice) = two types in sequence. The word "sequence" in option C is the giveaway that it handles an ordered, multi-step confirmation process.