You send newly created purchase orders to a supplier via EDI, whereas quantity or price changes are transmitted by e-mail. What prerequisites must be met if you are using the condition technique for…
The correct answer is A. The Price and Quantity fields are relevant for printout changes. C. You have configured different message types for the New and Change print options. E. The New Message Determination Process for Change Messages indicator is flagged in. In SAP message determination using the condition technique, sending new POs via EDI and changes via email requires three things to work together: the system must know which field changes matter (A), must have separate message types to route to different channels (C), and must…
Question
You send newly created purchase orders to a supplier via EDI, whereas quantity or price changes are transmitted by e-mail. What prerequisites must be met if you are using the condition technique for message determination? Note: There are 3 correct answers to this question.
Options
- AThe Price and Quantity fields are relevant for printout changes.
- BThe condition record contains the Price and Quantity fields.
- CYou have configured different message types for the New and Change print options.
- DThe dispatch time related to the change message needs to be set to 1 (send with periodically
- EThe New Message Determination Process for Change Messages indicator is flagged in
How the community answered
(24 responses)- A79% (19)
- B13% (3)
- D8% (2)
Explanation
In SAP message determination using the condition technique, sending new POs via EDI and changes via email requires three things to work together: the system must know which field changes matter (A), must have separate message types to route to different channels (C), and must be told to re-run message determination when a change occurs (E). Without flagging Price and Quantity as change-relevant (A), the system won't detect that a meaningful change happened. Without distinct message types for New vs. Change (C), there's no way to assign EDI to one and email to the other. Without the "New Message Determination Process for Change Messages" indicator (E), the system simply won't trigger a fresh determination when the PO is changed.
Why B is wrong: Condition records store output type, medium, and timing - not business fields like Price or Quantity. Those fields live in change-relevance configuration, not in the condition record itself.
Why D is wrong: Dispatch time 1 (periodic job) is one scheduling option, but it is not a prerequisite - the change message could be sent immediately or via another timing option. No specific dispatch time is mandated for this setup to work.
Memory tip: Think of the acronym ACE - Alert the system to relevant fields, Create separate message types, Enable new determination for changes. All three are needed before the system can intelligently split EDI (new) from email (change).