Which of the following can you control with the confirmation control key? Note: There are 2 correct answers to this question.

The correct answer is A. Whether a goods receipt needs to be confirmed D. Whether a confirmation type is a prerequisite for a goods receipt. In SAP Production Planning, the confirmation control key governs confirmation behavior at the operation level and directly ties confirmation to goods receipt processing. Option A is correct because the key determines whether posting a goods receipt must accompany or be…

Configuration of Purchasing

Question

Which of the following can you control with the confirmation control key? Note: There are 2 correct answers to this question.

Options

  • AWhether a goods receipt needs to be confirmed
  • BWhether reminders for outstanding confirmations are required
  • CWhether a confirmation type is relevant for MRP
  • DWhether a confirmation type is a prerequisite for a goods receipt

How the community answered

(60 responses)
  • A
    83% (50)
  • B
    5% (3)
  • C
    12% (7)

Explanation

In SAP Production Planning, the confirmation control key governs confirmation behavior at the operation level and directly ties confirmation to goods receipt processing. Option A is correct because the key determines whether posting a goods receipt must accompany or be triggered by a confirmation. Option D is correct because the key can enforce that a confirmation is a mandatory prerequisite before a goods receipt can be posted at all - preventing GR without a prior confirmation.

Option B is wrong because reminder settings for outstanding confirmations are managed through separate workflow or scheduling configurations, not the confirmation control key. Option C is wrong because MRP relevance is controlled at the operation/work center or routing level, not through the confirmation control key.

Memory tip: Think of the confirmation control key as the "GR gatekeeper" - its two jobs are deciding if a GR is needed with a confirmation (A) and whether confirmation must come before the GR (D). Anything about reminders or MRP lives elsewhere in customizing.

Topics

#confirmation control key#goods receipt prerequisite#MRP relevance#order acknowledgment