C_TS452_2410 · Question #61
Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.
The correct answer is B. Carry out a lot-size calculation for every material with net requirements C. Carry out a net requirement calculation for every material included in the planning run. During reorder point planning, the system evaluates every material in the planning run against its reorder point, making net requirements calculation (C) a core step - if stock falls below the reorder point, a shortage is identified. From there, the system applies the…
Question
Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.
Options
- AFlag materials that have been subject to an activity relevant to MRP
- BCarry out a lot-size calculation for every material with net requirements
- CCarry out a net requirement calculation for every material included in the planning run
- DPerform backward scheduling to determine the availability dates of purchase requisitions
How the community answered
(51 responses)- A20% (10)
- B71% (36)
- D10% (5)
Explanation
During reorder point planning, the system evaluates every material in the planning run against its reorder point, making net requirements calculation (C) a core step - if stock falls below the reorder point, a shortage is identified. From there, the system applies the configured lot-sizing procedure to determine how much to order, making lot-size calculation (B) the natural follow-up step.
Why the distractors are wrong:
- A is wrong because flagging materials with MRP-relevant changes (the "MRP flag") applies to net change MRP planning, not reorder point planning. Reorder point planning checks all included materials regardless of recent activity.
- D is wrong because backward scheduling (calculating start dates by working backwards from a due date) is a feature of standard MRP and production planning, not reorder point planning, which uses simpler replenishment lead time calculations.
Memory tip: Reorder point planning has two core jobs - find the gap (net requirements) and fill the gap (lot-size calculation). Think of it as "Gap → Fill" = C → B.