C_TS452_2410 · Question #57

During reorder point planning, which time elements does the forward scheduling procedure take into account when calculating the availability date? There are 3 correct answers to this question.

The correct answer is A. Purchasing department processing time C. Goods receipt processing time D. Planned delivery time. In forward scheduling during reorder point planning, SAP calculates the availability date by projecting forward from today's date using the three time components that represent the real procurement timeline: A (Purchasing department processing time): The time your internal…

Consumption-Based Planning

Question

During reorder point planning, which time elements does the forward scheduling procedure take into account when calculating the availability date? There are 3 correct answers to this question.

Options

  • APurchasing department processing time
  • BTotal shelf life
  • CGoods receipt processing time
  • DPlanned delivery time
  • EGoods issue processing time

How the community answered

(47 responses)
  • A
    74% (35)
  • B
    9% (4)
  • E
    17% (8)

Explanation

In forward scheduling during reorder point planning, SAP calculates the availability date by projecting forward from today's date using the three time components that represent the real procurement timeline:

  • A (Purchasing department processing time): The time your internal purchasing team needs to create and send a purchase order - a genuine delay before the vendor even starts working.
  • C (Goods receipt processing time): The time needed to inspect, unpack, and put away materials after physical arrival - stock isn't available until this step completes.
  • D (Planned delivery time): The vendor's lead time to produce and ship the material - the core external wait.

Why B and E are wrong: Total shelf life (B) is a quality/expiration parameter used in shelf-life planning, not in scheduling the procurement timeline. Goods issue processing time (E) is relevant to backward scheduling for production/customer orders (time to pick and stage material going out), not for calculating when an incoming replenishment will be available.

Memory tip: Think of the three steps a purchase order travels - Purchasing sends it → vendor Delivers it → warehouse Goods-receipts it. That's P-D-G (A, D, C) - the three forward-scheduling time buckets in order of occurrence.

Topics

#reorder point planning#forward scheduling#availability date#goods receipt processing time

Community Discussion

No community discussion yet for this question.