C_TS412_2021 · Question #39
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
The correct answer is A. The network activity is assigned to a WBS element C. The material master of the component must permit project stock management D. The Project Stock indicator is set in the project definition (non-valuated or valuated). To generate project stock reservations for a component assigned to a network activity, the following prerequisites must be met: The network activity must be assigned to a WBS element that is relevant for project stock The material master of the component must have a procurement…
Question
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
Options
- AThe network activity is assigned to a WBS element
- BThe network is assigned to a sales order item
- CThe material master of the component must permit project stock management
- DThe Project Stock indicator is set in the project definition (non-valuated or valuated)
- EA procurement indicator must be assigned to the activity
How the community answered
(22 responses)- A73% (16)
- B18% (4)
- E9% (2)
Explanation
To generate project stock reservations for a component assigned to a network activity, the following prerequisites must be met: The network activity must be assigned to a WBS element that is relevant for project stock The material master of the component must have a procurement type that allows project stock management (such as E, F, or X) and an individual/collective requirements indicator that allows individual requirements (such as 2 or 4). The project definition must have the Project Stock indicator set to either non-valuated or valuated