Question
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question
Options
- AThe network activity is assigned to a WBS element
- BThe network is assigned to a sales order item
- CThe material master of the component must permit project stock management
- DThe Project Stock indicator is set in the project definition (non-valuated or valuated)
- EA procurement indicator must be assigned to the activity