C_TS412_2021 · Question #30

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is…

The correct answer is D. The scheduling parameters for the network. To control whether the delivery date for an external component assigned to a network activity is defined by the earliest or latest scheduled dates, you can use the scheduling parameters for the network. An external component is a material component that is required for…

Materials in Project Systems

Question

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?

Options

  • AThe network profile
  • BThe control key
  • CThe table of MRP controllers
  • DThe scheduling parameters for the network

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    13% (6)
  • D
    79% (38)

Explanation

To control whether the delivery date for an external component assigned to a network activity is defined by the earliest or latest scheduled dates, you can use the scheduling parameters for the network. An external component is a material component that is required for executing a network activity and that is procured externally from vendors or other plants

Topics

#external components#purchase requisition#delivery date#scheduling parameters