What options are available in the maintenance order when you analyze costs using value categories? (Choose two)

The correct answer is B. Display of costs by individual operations D. Summary of actual costs across multiple cost elements. See the full explanation below for the reasoning.

Question

What options are available in the maintenance order when you analyze costs using value categories? (Choose two)

Options

  • ADisplay of costs by responsible work center
  • BDisplay of costs by individual operations
  • CDisplay of values in an alternate currency
  • DSummary of actual costs across multiple cost elements

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    78% (28)
  • C
    17% (6)

Community Discussion