nerdexam
SAP

C_TPLM30_66 · Question #76

A maintenance work order has external processing. The planning plant and maintenance plant have different addresses. A purchase requisition is generated from a maintenance order. With standard…

The correct answer is C. Planning plant. See the full explanation below for the reasoning.

Question

A maintenance work order has external processing. The planning plant and maintenance plant have different addresses. A purchase requisition is generated from a maintenance order. With standard delivered SAP Customizing, which address is the default delivery address in the purchase requisition?

Options

  • AWork center
  • BStorage location
  • CPlanning plant
  • DMaintenance plant

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    74% (14)
  • D
    16% (3)

Community Discussion

No community discussion yet for this question.

Full C_TPLM30_66 Practice