A user has planned an operation with labor costs and material costs; however, the material cost element is not assigned to a value category. Where do the material costs appear in the value…

The correct answer is C. In the unassigned value category. See the full explanation below for the reasoning.

Question

A user has planned an operation with labor costs and material costs; however, the material cost element is not assigned to a value category. Where do the material costs appear in the value categories for the order?

Options

  • AIn the overhead value category
  • BIn a new, automatically created value category
  • CIn the unassigned value category
  • DIn the internal activity value category

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    16% (5)
  • C
    74% (23)
  • D
    6% (2)