C_TPLM30_66 · Question #64

Which of the following steps must you perform to customize priorities for a maintenance order?

The correct answer is A. Assign a priority type to an order type. See the full explanation below for the reasoning.

Question

Which of the following steps must you perform to customize priorities for a maintenance order?

Options

  • AAssign a priority type to an order type.
  • BAssign priorities to technical object master records.
  • CAssign a priority type to a technical object master record.
  • DAssign priorities to order types.

How the community answered

(33 responses)
  • A
    76% (25)
  • B
    3% (1)
  • C
    15% (5)
  • D
    6% (2)