Users need to be able to select operations and work centers from the task list when they create a maintenance order with task list selection. In Customizing, how can you accomplish this requirement?…
The correct answer is C. By activating the work center selection indicator D. By activating the operation selection indicator. See the full explanation below for the reasoning.
Question
Users need to be able to select operations and work centers from the task list when they create a maintenance order with task list selection. In Customizing, how can you accomplish this requirement? (Choose two)
Options
- ABy setting the indicators for the order type only
- BBy setting the indicators for the planning plant only
- CBy activating the work center selection indicator
- DBy activating the operation selection indicator
How the community answered
(44 responses)- A7% (3)
- B16% (7)
- C77% (34)