nerdexam
SAP

C_TPLM22_64 · Question #28

Which of the following scenario doesn''t allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released? Please choose the correct…

The correct answer is A. The funds commitment in plan indicator is not set. See the full explanation below for the reasoning.

Question

Which of the following scenario doesn''t allow the plan value of the order to be added to the committed value of the WBS element until the order has the status released? Please choose the correct answer.

Options

  • AThe funds commitment in plan indicator is not set
  • BThe funds commitment in plan indicator is set to value less than 0
  • CThe funds commitment in plan indicator also has status released
  • DThe funds commitment in plan indicators is set

How the community answered

(40 responses)
  • A
    70% (28)
  • B
    5% (2)
  • C
    15% (6)
  • D
    10% (4)

Community Discussion

No community discussion yet for this question.

Full C_TPLM22_64 Practice