C_TPLM22_64 · Question #27
You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use? Please choose the correct answer.
The correct answer is D. Standard Milestones. See the full explanation below for the reasoning.
Question
You work with Project Builder (CJ20N) and want to use standard templates in your project structure. Which standard templates can you use? Please choose the correct answer.
Options
- AStandard cost planning
- BStandard Bill of Material (BOM)
- CStandard time scheduling
- DStandard Milestones
How the community answered
(54 responses)- A4% (2)
- B17% (9)
- C7% (4)
- D72% (39)