nerdexam
SAP

C_TFIN22_65 · Question #8

A customer wants you to explain the results of the preliminary costing of a production order. How are the results determined?

The correct answer is D. The quantity structure in the production order is valuated by the costing variant settings. The preliminary costing of a production order determines costs by valuating the production order's quantity structure (BOM and routing) using the parameters defined in the assigned costing variant.

Cost Object Controlling

Question

A customer wants you to explain the results of the preliminary costing of a production order. How are the results determined?

Options

  • AThe actual quantities are valuated with plan values.
  • BThe costs are determined by the cost estimate of the reference order.
  • CThe standard cost estimate is copied from the material master and adjusted by the order
  • DThe quantity structure in the production order is valuated by the costing variant settings.

How the community answered

(59 responses)
  • A
    7% (4)
  • B
    2% (1)
  • C
    3% (2)
  • D
    88% (52)

Why each option

The preliminary costing of a production order determines costs by valuating the production order's quantity structure (BOM and routing) using the parameters defined in the assigned costing variant.

AThe actual quantities are valuated with plan values.

Preliminary costing uses planned quantities from the order, not actual quantities, which are used for subsequent cost analyses.

BThe costs are determined by the cost estimate of the reference order.

While reference orders can exist, preliminary costing primarily relies on the specific order's quantity structure and its associated costing variant.

CThe standard cost estimate is copied from the material master and adjusted by the order

The standard cost estimate from the material master is a basis for target costing but is not directly copied and adjusted for preliminary order costing; instead, the order's specific structure and costing variant are used.

DThe quantity structure in the production order is valuated by the costing variant settings.Correct

Preliminary costing for a production order leverages the quantity structure, which includes the Bill of Material (BOM) for components and the routing for activities, present within the production order itself. These quantities are then valuated using the pricing strategies, overheads, and other settings defined in the costing variant assigned to the production order type.

Concept tested: Production order preliminary costing

Source: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f50123594a044415a770857022513f1c/1e07b65381cf2614e10000000a174cb4.html

Topics

#Preliminary costing#Production order#Costing variant#Quantity structure

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_65 Practice