C_TFIN22_65 · Question #10

A customer wants to allocate overhead costs to a production order. How can the customer achieve that? Note: There are 3 correct answers to this question.

The correct answer is A. Use routings and work centers. C. Use a template. D. Use a costing sheet. Overhead costs can be allocated to a production order through routings and work centers (via activity types), by using a costing sheet, or by employing templates.

Cost Object Controlling

Question

A customer wants to allocate overhead costs to a production order. How can the customer achieve that? Note: There are 3 correct answers to this question.

Options

  • AUse routings and work centers.
  • BDefine an assessment cycle.
  • CUse a template.
  • DUse a costing sheet.
  • EUse indirect activity allocation.

How the community answered

(17 responses)
  • A
    88% (15)
  • B
    6% (1)
  • E
    6% (1)

Why each option

Overhead costs can be allocated to a production order through routings and work centers (via activity types), by using a costing sheet, or by employing templates.

AUse routings and work centers.Correct

Routings and work centers define the activities (e.g., machine time, labor) required for production. These activities are associated with activity types, which carry rates that include primary costs and potentially overheads, thus transferring costs to the production order.

BDefine an assessment cycle.

Assessment cycles are used for periodic allocation of costs from cost centers to other cost objects, but not typically for directly applying overhead to individual production orders.

CUse a template.Correct

Templates allow for the flexible allocation of overhead costs based on specific business processes or characteristics of the production order, offering a dynamic way to assign costs.

DUse a costing sheet.Correct

A costing sheet is a central configuration tool in product costing that defines how overhead surcharges are calculated and applied to material and activity costs on a production order.

EUse indirect activity allocation.

Indirect activity allocation is used for allocating activity costs that cannot be directly measured, usually from sender cost centers to receiver cost centers or orders, but is distinct from applying overheads via costing sheets or templates to a production order.

Concept tested: Production order overhead allocation methods

Source: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f50123594a044415a770857022513f1c/1e07b65381cf2614e10000000a174cb4.html

Topics

#Overhead allocation#Production order costing#Costing sheet#Templates