How is Work in Process (WIP) calculated on a product cost collector?

The correct answer is D. Based on target cost, depending on the valuation variant settings. Work in Process (WIP) on a product cost collector is calculated based on target cost, and its valuation is determined by the valuation variant settings.

Cost Object Controlling

Question

How is Work in Process (WIP) calculated on a product cost collector?

Options

  • ABased on the standard cost estimate, independent of the valuation variant settings.
  • BBased on the target cost, depending on the order type settings.
  • CBased on actual cost, depending on the order status.
  • DBased on target cost, depending on the valuation variant settings.

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    2% (1)
  • D
    93% (40)

Why each option

Work in Process (WIP) on a product cost collector is calculated based on target cost, and its valuation is determined by the valuation variant settings.

ABased on the standard cost estimate, independent of the valuation variant settings.

While standard cost estimates are a basis for target costs, WIP calculation is NOT independent of valuation variant settings; the valuation variant specifically defines how target costs are determined for WIP.

BBased on the target cost, depending on the order type settings.

WIP is based on target costs but the specific valuation method for these target costs (and thus WIP) is determined by the valuation variant, not directly by the order type settings. The order type settings link to the valuation variant.

CBased on actual cost, depending on the order status.

WIP is not calculated based solely on actual cost; it involves a comparison of actual costs with target costs to determine the value of unfinished goods.

DBased on target cost, depending on the valuation variant settings.Correct

WIP calculation for product cost collectors generally compares actual costs incurred to the target costs for the quantity produced or processed. The target costs themselves are typically derived from a standard cost estimate, and the valuation variant specified in the WIP calculation settings determines how these target costs are valued (e.g., at standard cost, planned cost, or another method).

Concept tested: WIP calculation on product cost collectors

Source: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f50058b757e94e50882e5058682126ae/45f95f4b9fe311d1891b0000e8322d00.html

Topics

#Work in Process (WIP)#Product cost collector#Target cost#Valuation variant

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_65 Practice