C_TFIN22_65 · Question #33
A customer asks you to explain the category price variances received on production orders. What could be the reason for price variances? Note: There are 2 correct answers to this question.
The correct answer is B. The master data of the consumed materials is V price indicated. C. The valuation variants of the cost estimate and the production order are different. Price variances on production orders can arise when consumed materials are valuated at a moving average price (V price) or when the valuation strategies used in the cost estimate and the production order differ.
Question
A customer asks you to explain the category price variances received on production orders. What could be the reason for price variances? Note: There are 2 correct answers to this question.
Options
- AThe activity types were consumed from different cost centers.
- BThe master data of the consumed materials is V price indicated.
- CThe valuation variants of the cost estimate and the production order are different.
- DThe respective routing has changed.
How the community answered
(38 responses)- A21% (8)
- B68% (26)
- D11% (4)
Why each option
Price variances on production orders can arise when consumed materials are valuated at a moving average price (V price) or when the valuation strategies used in the cost estimate and the production order differ.
Consuming activity types from different cost centers typically leads to quantity variances or rate variances, but not specifically 'price variances' in the context of material input.
If consumed materials are managed with a V price (moving average price), any difference between the planned price used in the standard cost estimate and the actual moving average price at the time of goods issue to the production order will result in a price variance.
Price variances can occur if the valuation variant used for the standard cost estimate (which determines planned costs) is different from the valuation variant used for valuing actual costs on the production order. Different valuation variants can lead to different activity rates or material prices being used, causing a variance.
A change in the routing would primarily lead to quantity variances (due to different activity consumption or setup times) or possibly resource-related variances, rather than a direct 'price variance' on material input or activity rates themselves.
Concept tested: Production order price variance causes
Source: https://help.sap.com/docs/SAP_ERP_SPV/5a918a99266f44618e404b998246e499/c61b185351a62d4be10000000a44176d.html