How can you achieve periodic controlling when a lot size based production scenario is used by logistics? Note: There are 2 correct answers to this question.

The correct answer is A. Adjust the default rule in the default values for the production order type. C. Use a product cost collector in addition to the production order. To achieve periodic controlling in a lot-size-based production scenario, you can adjust the default rule for the production order type or use a product cost collector alongside the production order.

Cost Object Controlling

Question

How can you achieve periodic controlling when a lot size based production scenario is used by logistics? Note: There are 2 correct answers to this question.

Options

  • AAdjust the default rule in the default values for the production order type.
  • BUse an internal order in addition to the production order.
  • CUse a product cost collector in addition to the production order.
  • DAdjust the costing type of the plan costing variant.

How the community answered

(59 responses)
  • A
    75% (44)
  • B
    17% (10)
  • D
    8% (5)

Why each option

To achieve periodic controlling in a lot-size-based production scenario, you can adjust the default rule for the production order type or use a product cost collector alongside the production order.

AAdjust the default rule in the default values for the production order type.Correct

The default rule in the production order type determines how costs are settled and managed. By setting it to a rule that supports periodic settlement (e.g., PP2 - Production Material Period Settlement), the system can perform periodic controlling for lot-size-based orders.

BUse an internal order in addition to the production order.

Using an internal order in addition to a production order would typically introduce another layer of cost collection, but not directly enable periodic controlling for the production order itself in this context.

CUse a product cost collector in addition to the production order.Correct

Using a product cost collector in conjunction with production orders allows for period-based actual costing. The costs from multiple production orders for the same material are collected on the product cost collector, which is then settled periodically.

DAdjust the costing type of the plan costing variant.

Adjusting the costing type of the plan costing variant primarily affects how standard or planned costs are calculated, not how actual costs are collected and settled periodically for production orders.

Concept tested: Periodic controlling in production scenarios

Source: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/f50123594a044415a770857022513f1c/0d01a25381cf2614e10000000a174cb4.html

Topics

#Periodic controlling#Lot-size production#Product Cost Collector#Production order settlement

Community Discussion

No community discussion yet for this question.

Full C_TFIN22_65 Practice