BA-201 · Question #89
The Salesforce project team at Universal Containers is reviewing a backlog of user stories to add to an sprint. The team is unsure of which story to begin working on. What should the business…
The correct answer is B. Identify dependent components. When a team is unsure which user story to work on first, the business analyst should identify dependent components. Dependencies between stories determine which work must be completed before other stories can begin - skipping this step can cause blockers mid-sprint. Verifying…
Question
The Salesforce project team at Universal Containers is reviewing a backlog of user stories to add to an sprint. The team is unsure of which story to begin working on. What should the business analyst do to help with prioritization?
Options
- AVerify acceptance criteria.
- BIdentify dependent components.
- CDelete the definition of done
How the community answered
(16 responses)- A6% (1)
- B88% (14)
- C6% (1)
Explanation
When a team is unsure which user story to work on first, the business analyst should identify dependent components. Dependencies between stories determine which work must be completed before other stories can begin - skipping this step can cause blockers mid-sprint. Verifying acceptance criteria (A) ensures a story is well-defined but does not help with ordering. Deleting the definition of done (C) is never appropriate, as it removes the shared standard for when work is complete.