BA-201 · Question #89

BA-201 Question #89: Real Exam Question with Answer & Explanation

The correct answer is B: Identify dependent components.. The business analyst should identify dependent components to help with prioritization of user stories to add to an sprint. Dependent components are components that rely on or affect other components in an application or system. Identifying dependent components can help determine

Elicit & Analyze

Question

The Salesforce project team at Universal Containers is reviewing a backlog of user stories to add to an sprint. The team is unsure of which story to begin working on. What should the business analyst do to help with prioritization?

Options

  • AVerify acceptance criteria.
  • BIdentify dependent components.
  • CDelete the definition of done

Explanation

The business analyst should identify dependent components to help with prioritization of user stories to add to an sprint. Dependent components are components that rely on or affect other components in an application or system. Identifying dependent components can help determine which user stories are more critical, complex, risky, or interrelated than others and prioritize them accordingly. Identifying dependent components can also help avoid conflicts, errors, or delays caused by missing or incompatible components when developing or deploying user stories. Verifying acceptance criteria is not an action that the business analyst should take to help with prioritization of user stories to add to an sprint. Verifying acceptance criteria is a process that checks whether a user story meets its conditions or requirements for being done or acceptable. Verifying acceptance criteria can help validate and test user stories but does not help prioritize them based on their importance or urgency. Deleting the definition of done is not an action that the business analyst should take to help with prioritization of user stories to add to an sprint. Deleting the definition of done is a process that removes the criteria or standards that indicate when a user story is completed and ready for deployment. Deleting the definition of done can reduce quality and consistency of user stories but does not help prioritize them based on their importance or urgency. https://trailhead.salesforce.com/en/content/learn/modules/salesforce-business-analyst- certification-prep/user-stories

Topics

#Prioritization#Dependencies#User Stories#Sprint Planning