BA-201 · Question #62
Over the past month, a business analyst (BA) has worked with various stakeholders at Cloud Kicks to document requirements for an upcoming Tableau implementation. A stakeholder suggested a revision to
The correct answer is A. Statement of work. The Statement of Work (SOW) is a formal project document that records project scope, deliverables, and key milestones - including requirements sign-off events. Getting stakeholder sign-off on revised requirements is a formal milestone that should be recorded in the SOW to reflect
Question
Over the past month, a business analyst (BA) has worked with various stakeholders at Cloud Kicks to document requirements for an upcoming Tableau implementation. A stakeholder suggested a revision to the requirements. The BA sent the updated requirements to the stakeholders and they signed off. Where should the BA track this milestone?
Options
- AStatement of work
- BChange log
- CSprint plan
How the community answered
(27 responses)- A81% (22)
- B7% (2)
- C11% (3)
Explanation
The Statement of Work (SOW) is a formal project document that records project scope, deliverables, and key milestones - including requirements sign-off events. Getting stakeholder sign-off on revised requirements is a formal milestone that should be recorded in the SOW to reflect the agreed-upon scope at that point in time. A change log (Option B) is used to track what changed and why, but it does not serve as the milestone-tracking record. A sprint plan (Option C) is an agile planning artifact for tracking sprint-level work, not formal project milestones or approvals.