BA-201 · Question #201

BA-201 Question #201: Real Exam Question with Answer & Explanation

The correct answer is C: Small. The checklist item that is the most likely reason why the stories are incomplete at the close of the sprint is small. Small means that a user story should be simple and concise, and it should be able to be completed within a single sprint by a single developer or a small team. A

Elicit & Analyze

Question

The Salesforce delivery team at Cloud Kicks consistently has user stories that developers start but are unable to complete during each sprint. During the most recent retrospective, the development team expressed that they are running out of time to complete the stories. The team used the INVEST checklist to diagnose why these stories are incomplete at the end of the sprint. Which checklist item is the most likely reason why the stories are incomplete at the close of the sprint?

Options

  • ANegotiable
  • BValuable
  • CSmall

Explanation

The checklist item that is the most likely reason why the stories are incomplete at the close of the sprint is small. Small means that a user story should be simple and concise, and it should be able to be completed within a single sprint by a single developer or a small team. A user story that is too large or complex may be difficult to estimate, prioritize, test, or deliver within the sprint timeframe. A user story that is too small may be trivial, redundant, or irrelevant to the project goals. A user story that is not small enough may need to be broken down into smaller and more manageable chunks. https://trailhead.salesforce.com/content/learn/modules/user-story-creation/write-user-stories

Topics

#User Stories#INVEST Principle#Agile Sprints#Sprint Management