BA-201 · Question #183
Northern Trail Outfitters (NTO) has completed a project with a third-party event organization platform to enhance its MVP Experience Site. Many features were left in the project backlog. NTO's IT…
The correct answer is C. Prioritize user stories for the new enhancements for the initial sprints of the project to. When beginning a new project phase, the BA should prioritize user stories for the new enhancements in the initial sprints (Choice C). The new business stakeholder requests represent the current, actively prioritized business needs that are driving this new phase. Old backlog…
Question
Northern Trail Outfitters (NTO) has completed a project with a third-party event organization platform to enhance its MVP Experience Site. Many features were left in the project backlog. NTO's IT team is beginning a new phase of work on the Experience Site to build additional features requested by business stakeholders and wants to include the items that were left in the backlog in the first phase. How should the business analyst coordinate the user stories to most efficiently manage the new project timeline?
Options
- AInclude existing and new user stories to be completed within the duration of the project. Hire
- BReprioritize existing and new user storks to place the stories into each sprint of the project.
- CPrioritize user stories for the new enhancements for the initial sprints of the project to
How the community answered
(46 responses)- A7% (3)
- B13% (6)
- C80% (37)
Explanation
When beginning a new project phase, the BA should prioritize user stories for the new enhancements in the initial sprints (Choice C). The new business stakeholder requests represent the current, actively prioritized business needs that are driving this new phase. Old backlog items from the previous phase may have lower or shifted priority, and should be re-evaluated and incorporated into later sprints after current priorities are addressed. Choice A (hiring additional resources immediately) introduces unnecessary cost and overhead before scope is even fully defined. Choice B (immediately reprioritizing all old and new stories together) could delay delivery of the highest-value new features by mixing them indiscriminately with potentially stale backlog items. Addressing new priorities first ensures the team delivers maximum current business value.