BA-201 · Question #140
The business analyst (BA) at Cloud Kicks is deep in planning activities for its Commerce C oud implementation project. The project sponsor asks the team to.. their efforts due to budgetary constraints
The correct answer is B. Ask the project manage to re-prioritize .. requirements.. When the project sponsor asks the team to scale back due to budgetary constraints, the appropriate BA action is to ask the project manager to re-prioritize requirements. This directly addresses the budget constraint by reducing scope to the highest-value items. Asking to increase
Question
The business analyst (BA) at Cloud Kicks is deep in planning activities for its Commerce C oud implementation project. The project sponsor asks the team to.. their efforts due to budgetary constraints. What should the BA do next?
Options
- AAsk the project sponsor to increase the project budget.
- BAsk the project manage to re-prioritize .. requirements.
- CAsk the project sponsor to request additional resources.
How the community answered
(21 responses)- A5% (1)
- B81% (17)
- C14% (3)
Explanation
When the project sponsor asks the team to scale back due to budgetary constraints, the appropriate BA action is to ask the project manager to re-prioritize requirements. This directly addresses the budget constraint by reducing scope to the highest-value items. Asking to increase the budget (A) ignores the stated constraint, and requesting additional resources (C) would increase costs, making the budget problem worse. Re-prioritization is the standard response to a reduced budget - deliver the most valuable requirements first within the new constraint.
Topics