ASF · Question #13
Who is the owner of a Sprint Backlog Item during the Sprint Planning meeting?
The correct answer is A. The entire team owns all Sprint Backlog Items. In Scrum, the entire Development Team collectively owns the Sprint Backlog, meaning no single individual "owns" any item - the team self-organizes and shares responsibility for delivering the Sprint Goal together. Option B is wrong because the Product Owner owns the Product…
Question
Who is the owner of a Sprint Backlog Item during the Sprint Planning meeting?
Options
- AThe entire team owns all Sprint Backlog Items.
- BThe Product Owner owns all Sprint Backlog Items.
- CThe team member working on the item owns that item.
How the community answered
(34 responses)- A91% (31)
- B6% (2)
- C3% (1)
Explanation
In Scrum, the entire Development Team collectively owns the Sprint Backlog, meaning no single individual "owns" any item - the team self-organizes and shares responsibility for delivering the Sprint Goal together.
Option B is wrong because the Product Owner owns the Product Backlog, not the Sprint Backlog; during Sprint Planning, the team pulls items in and takes collective ownership of them.
Option C is wrong because even when one person works on a task, Scrum treats it as a team commitment - if that person gets blocked, the whole team is responsible for resolving it.
Memory tip: Think of the Sprint Backlog as a shared team contract, not a task assignment list. The word "team" appears in every Scrum accountability that touches the Sprint - if an answer says "individual," it's almost always a distractor.