nerdexam
EXIN

ASF · Question #50

During a Sprint Planning session, the team argues about the work estimates for a particular story. - The Product Owner estimates five days. - The Lead Architect estimates two days. - The Scrum…

The correct answer is C. 7. In Scrum, estimates must come from the person who will actually perform the work - in this case, the team member who estimates 7 days. That individual has the most accurate understanding of the task's technical complexity and the effort required. Why the distractors are wrong…

Scrum Events

Question

During a Sprint Planning session, the team argues about the work estimates for a particular story.

  • The Product Owner estimates five days.
  • The Lead Architect estimates two days.
  • The Scrum Master estimates eight days.
  • The team member working on it estimates seven days.

What value (in days) should be used for planning?

Options

  • A2
  • B5
  • C7
  • D8

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    3% (1)
  • C
    79% (23)
  • D
    10% (3)

Explanation

In Scrum, estimates must come from the person who will actually perform the work - in this case, the team member who estimates 7 days. That individual has the most accurate understanding of the task's technical complexity and the effort required.

Why the distractors are wrong:

  • A (2 days - Lead Architect): Architects often underestimate hands-on implementation effort; unless they are doing the work, their estimate is not authoritative.
  • B (5 days - Product Owner): The PO owns the what, not the how. Estimating development effort is explicitly outside their role in Scrum.
  • D (8 days - Scrum Master): The Scrum Master is a facilitator and servant-leader, not a developer; they should not be estimating task duration.

Memory tip: Think "The doer decides." The estimate always belongs to the person with their hands on the keyboard - if you can identify who is implementing the story, that's whose number you use.

Topics

#Sprint Planning#estimation authority#team self-organization#story sizing

Community Discussion

No community discussion yet for this question.

Full ASF Practice