ASF · Question #50
During a Sprint Planning session, the team argues about the work estimates for a particular story. - The Product Owner estimates five days. - The Lead Architect estimates two days. - The Scrum…
The correct answer is C. 7. In Scrum, estimates must come from the person who will actually perform the work - in this case, the team member who estimates 7 days. That individual has the most accurate understanding of the task's technical complexity and the effort required. Why the distractors are wrong…
Question
During a Sprint Planning session, the team argues about the work estimates for a particular story.
- The Product Owner estimates five days.
- The Lead Architect estimates two days.
- The Scrum Master estimates eight days.
- The team member working on it estimates seven days.
What value (in days) should be used for planning?
Options
- A2
- B5
- C7
- D8
How the community answered
(29 responses)- A7% (2)
- B3% (1)
- C79% (23)
- D10% (3)
Explanation
In Scrum, estimates must come from the person who will actually perform the work - in this case, the team member who estimates 7 days. That individual has the most accurate understanding of the task's technical complexity and the effort required.
Why the distractors are wrong:
- A (2 days - Lead Architect): Architects often underestimate hands-on implementation effort; unless they are doing the work, their estimate is not authoritative.
- B (5 days - Product Owner): The PO owns the what, not the how. Estimating development effort is explicitly outside their role in Scrum.
- D (8 days - Scrum Master): The Scrum Master is a facilitator and servant-leader, not a developer; they should not be estimating task duration.
Memory tip: Think "The doer decides." The estimate always belongs to the person with their hands on the keyboard - if you can identify who is implementing the story, that's whose number you use.
Topics