ASF · Question #22
What is a Sprint?
The correct answer is C. One iteration in the Scrum methodology.. C is correct because a Sprint is the core time-boxed unit of work in Scrum - a fixed-length iteration (typically 1–4 weeks) during which the team delivers a potentially shippable product increment. Why the others are wrong: A is incorrect because brainstorming design ideas is not
Question
What is a Sprint?
Options
- AA brainstorming session in Extreme programming to generate design ideas.
- BA race between two developers to see who can complete a feature fastest.
- COne iteration in the Scrum methodology.
- DThe last iteration in the Scrum project, when the team works long hours to finish the project.
How the community answered
(54 responses)- A4% (2)
- B2% (1)
- C87% (47)
- D7% (4)
Explanation
C is correct because a Sprint is the core time-boxed unit of work in Scrum - a fixed-length iteration (typically 1–4 weeks) during which the team delivers a potentially shippable product increment.
Why the others are wrong:
- A is incorrect because brainstorming design ideas is not a Scrum concept at all; it conflates Scrum with Extreme Programming (XP) practices.
- B is a fictional concept - Scrum is collaborative, not competitive between developers.
- D describes a "crunch" anti-pattern, which contradicts Scrum's principle of sustainable pace; no single Sprint is designated as "the last one" where the team overworks.
Memory tip: Think of a Sprint like a sprint in athletics - it's a short, focused burst of effort with a clear start and finish line, not a marathon or a race against a teammate.