What is the expected outcome of the first Sprint on a project?

The correct answer is A. A few working, tested features from the Product Backlog. In Scrum, a Sprint always ends with a potentially shippable product increment - meaning real, working, tested software. Even the very first Sprint is expected to deliver a small slice of functionality pulled from the Product Backlog, not just plans or paperwork. B is wrong…

Scrum Events

Question

What is the expected outcome of the first Sprint on a project?

Options

  • AA few working, tested features from the Product Backlog
  • BArchitecture and high-level design of the Product
  • CAssignment of the team, Product Owner and Scrum Master
  • DA well-defined release plan for the Product

How the community answered

(56 responses)
  • A
    93% (52)
  • B
    2% (1)
  • C
    4% (2)
  • D
    2% (1)

Explanation

In Scrum, a Sprint always ends with a potentially shippable product increment - meaning real, working, tested software. Even the very first Sprint is expected to deliver a small slice of functionality pulled from the Product Backlog, not just plans or paperwork.

  • B is wrong because Scrum deliberately avoids big upfront architecture work. Design emerges incrementally across Sprints.
  • C is wrong because team formation and role assignment happen before Sprint 1, during project initiation - not as a Sprint output.
  • D is wrong because Scrum discourages rigid long-range release plans. The roadmap is refined continuously, not locked in after one Sprint.

Memory tip: Think of every Sprint - including Sprint 1 - as a mini-project that must end with working software. If it doesn't ship something testable, it's not a valid Sprint outcome.

Topics

#first Sprint#Sprint outcome#working software#product increment