ASF · Question #12
What is the expected outcome of the first Sprint on a project?
The correct answer is A. A few working, tested features from the Product Backlog. In Scrum, a Sprint always ends with a potentially shippable product increment - meaning real, working, tested software. Even the very first Sprint is expected to deliver a small slice of functionality pulled from the Product Backlog, not just plans or paperwork. B is wrong…
Question
What is the expected outcome of the first Sprint on a project?
Options
- AA few working, tested features from the Product Backlog
- BArchitecture and high-level design of the Product
- CAssignment of the team, Product Owner and Scrum Master
- DA well-defined release plan for the Product
How the community answered
(56 responses)- A93% (52)
- B2% (1)
- C4% (2)
- D2% (1)
Explanation
In Scrum, a Sprint always ends with a potentially shippable product increment - meaning real, working, tested software. Even the very first Sprint is expected to deliver a small slice of functionality pulled from the Product Backlog, not just plans or paperwork.
- B is wrong because Scrum deliberately avoids big upfront architecture work. Design emerges incrementally across Sprints.
- C is wrong because team formation and role assignment happen before Sprint 1, during project initiation - not as a Sprint output.
- D is wrong because Scrum discourages rigid long-range release plans. The roadmap is refined continuously, not locked in after one Sprint.
Memory tip: Think of every Sprint - including Sprint 1 - as a mini-project that must end with working software. If it doesn't ship something testable, it's not a valid Sprint outcome.