Which statement applies to the DSDM process?

The correct answer is A. Can be configured and calibrated to cater for light or strong governance. The DSDM process can indeed be configured and calibrated to cater for a range of projects, from those requiring light governance to those needing stronger governance1. This flexibility allows the DSDM process to be tailored to the specific needs of the project, ensuring that…

The DSDM Process

Question

Which statement applies to the DSDM process?

Options

  • ACan be configured and calibrated to cater for light or strong governance
  • BDSDM projects can deliver the phases in the DSDM process in any order
  • CDoes not require the elaboration of supporting products for complex projects
  • DProvides an approach that can be used for all projects without change

How the community answered

(38 responses)
  • A
    71% (27)
  • B
    5% (2)
  • C
    13% (5)
  • D
    11% (4)

Explanation

The DSDM process can indeed be configured and calibrated to cater for a range of projects, from those requiring light governance to those needing stronger governance1. This flexibility allows the DSDM process to be tailored to the specific needs of the project, ensuring that the right balance between control and agility is achieved.

Topics

#DSDM process#governance#configuration#calibration