AGILEPM-FOUNDATION · Question #5
How does the Post-Project phase add value to a project?
The correct answer is C. Checks how well the expected business benefits have been met. The Post-Project phase in AgilePM is crucial for evaluating the project's success in terms of the business benefits realized. It is conducted after the project is completed and focuses on assessing whether the expected benefits outlined at the start of the project have been…
The DSDM Process
Question
How does the Post-Project phase add value to a project?
Options
- ADefine how the operation of the solution will be managed
- BIteratively explores the low- level detail of the requirements
- CChecks how well the expected business benefits have been met
- DBrigs a baseline of the Evolving Solution into operational use
How the community answered
(34 responses)- A3% (1)
- B9% (3)
- C85% (29)
- D3% (1)
Explanation
The Post-Project phase in AgilePM is crucial for evaluating the project's success in terms of the business benefits realized. It is conducted after the project is completed and focuses on assessing whether the expected benefits outlined at the start of the project have been achieved.
Topics
#Post-Project phase#Business benefits#DSDM lifecycle