AGILEPM-FOUNDATION · Question #19

What phase will decide on which projects are started, based on a clearly defined objective?

The correct answer is A. Pre-Project. The Pre-Project phase is the stage where it is decided which projects are started, based on a clearly defined objective1. This phase ensures that only the right projects are initiated and that they are set up correctly, aligning with the DSDM philosophy that the best business…

The DSDM Process

Question

What phase will decide on which projects are started, based on a clearly defined objective?

Options

  • APre-Project
  • BFeasibility
  • CFoundations
  • DPost-project

How the community answered

(43 responses)
  • A
    91% (39)
  • B
    2% (1)
  • C
    2% (1)
  • D
    5% (2)

Explanation

The Pre-Project phase is the stage where it is decided which projects are started, based on a clearly defined objective1. This phase ensures that only the right projects are initiated and that they are set up correctly, aligning with the DSDM philosophy that the best business value emerges when projects are aligned to clear business goals.

Topics

#Pre-Project phase#DSDM lifecycle#Project initiation