AGILEPM-FOUNDATION · Question #13
During what phase should a baseline of the Evolving Solution be put into operational use?
The correct answer is C. Deployment. A baseline of the Evolving Solution should be put into operational use during the Deployment phase. This phase is when the latest increment of the product is put into live use, marking the transition from development to real-world operation.
The DSDM Process
Question
During what phase should a baseline of the Evolving Solution be put into operational use?
Options
- AFoundations
- BEvolutionary Development
- CDeployment
- DPost-Project
How the community answered
(25 responses)- A4% (1)
- C92% (23)
- D4% (1)
Explanation
A baseline of the Evolving Solution should be put into operational use during the Deployment phase. This phase is when the latest increment of the product is put into live use, marking the transition from development to real-world operation.
Topics
#Deployment phase#Evolving Solution#DSDM lifecycle