The correct answer is C. Managed by varying the features to be delivered.. In a DSDM project, contingency is typically managed by varying the features to be delivered6. This approach aligns with the DSDM principle of delivering the most critical work first and using the MoSCoW prioritization to adjust the scope of delivery as needed.

Question

How is contingency typically managed in a DSDM project?

Options

  • ANot needed in a DSDM project.
  • BAllowed adding a percentage to the high-level estimates.
  • CManaged by varying the features to be delivered.
  • DManaged by varying time and cost

Explanation

In a DSDM project, contingency is typically managed by varying the features to be delivered6. This approach aligns with the DSDM principle of delivering the most critical work first and using the MoSCoW prioritization to adjust the scope of delivery as needed.