How should DSDM team measure progress?

The correct answer is B. Based on what has been delivered at the end of a Timebox. A DSDM team should measure progress: B. Based on what has been delivered at the end of a

DSDM Philosophy and Principles

Question

How should DSDM team measure progress?

Options

  • AThrough a project dashboard
  • BBased on what has been delivered at the end of a Timebox.
  • CBased on the completion of activities rather than the delivery of products
  • DThrough an analysis of the Instrumental Success Factors.

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    90% (36)
  • C
    5% (2)
  • D
    3% (1)

Explanation

A DSDM team should measure progress: B. Based on what has been delivered at the end of a

Topics

#Progress measurement#Timebox#Product delivery#DSDM principles