AGILEPM-FOUNDATION · Question #80
In which Phase is the purpose to evolve a Solution that meets Business needs?
The correct answer is B. Evolutionary Development Phase. Option B is correct because the Evolutionary Development Phase (in DSDM) is where the team iteratively builds, refines, and tests the solution through timeboxed increments - progressively evolving it until it satisfies the agreed Business needs. A (Foundations Phase) is wrong…
Question
Options
- AFoundations Phase
- BEvolutionary Development Phase
- CPre-Project Phase
- DDeployment Phase
How the community answered
(26 responses)- A8% (2)
- B88% (23)
- C4% (1)
Explanation
Option B is correct because the Evolutionary Development Phase (in DSDM) is where the team iteratively builds, refines, and tests the solution through timeboxed increments - progressively evolving it until it satisfies the agreed Business needs.
- A (Foundations Phase) is wrong - this phase establishes understanding of the project: scope, architecture, and approach. It's about planning and agreement, not building the solution.
- C (Pre-Project Phase) is wrong - this phase determines whether a project is viable and worth initiating; no solution development occurs here.
- D (Deployment Phase) is wrong - by this phase the solution is already built; the focus is on releasing it into the live environment and ensuring user adoption.
Memory tip: Think "Evolutionary = Evolve." The word "evolve" appears in both the phase name and the question itself - if you see "evolve a Solution," map it directly to Evolutionary Development Phase.