AGILEPM-FOUNDATION · Question #73

At the Refinement stage of a structured timebox, what other factors, apart from the MoSCoW priorities, influence the order of work?

The correct answer is D. All of the above. Option D is correct because all three factors genuinely influence scheduling decisions during the Refinement stage - MoSCoW priority alone is not sufficient to determine the precise order of work within a timebox. A sensible technical development order matters because some…

DSDM Framework

Question

At the Refinement stage of a structured timebox, what other factors, apart from the MoSCoW priorities, influence the order of work?

Options

  • AA sensible development order from a technical perspective
  • BAvailability of specific resources such as Technical Advisors, Business Advisors
  • CAny known cross-team dependencies
  • DAll of the above

How the community answered

(65 responses)
  • A
    6% (4)
  • B
    5% (3)
  • C
    2% (1)
  • D
    88% (57)

Explanation

Option D is correct because all three factors genuinely influence scheduling decisions during the Refinement stage - MoSCoW priority alone is not sufficient to determine the precise order of work within a timebox. A sensible technical development order matters because some components must be built before others can function (e.g., a database layer before the UI that depends on it). Resource availability is a real constraint - if a specialist like a Technical or Business Advisor is only available at certain times, work requiring their input must be scheduled accordingly. Cross-team dependencies further constrain sequencing, since a team cannot complete work that relies on outputs from another team that hasn't delivered yet.

Options A, B, and C are not wrong on their own - they are each individually correct, which is precisely why choosing any single one over D would be the mistake. Exam takers who select A, B, or C are right about that factor but miss the point that all three apply simultaneously.

Memory tip: Think of the acronym TRD - Technical order, Resources, Dependencies. MoSCoW tells you what matters most; TRD tells you when you can actually do it. Whenever an exam question lists factors that are all legitimately true, suspect "All of the above" as the answer.

Topics

#timebox refinement#MoSCoW prioritization#DSDM process#work ordering