AGILEPM-FOUNDATION · Question #75
Between which phases of the DSDM process takes Evolutionary Development place?
The correct answer is D. Between Foundations and Deployment. Option D is correct because in the DSDM framework, the phases flow in this order: Pre-Project → Feasibility → Foundations → Evolutionary Development → Deployment → Post-Project. Evolutionary Development is where iterative prototyping and incremental builds occur - it sits after…
Question
Options
- ABetween Feasibility and Foundation
- BBetween Deployment and Post Project
- CBetween Pre-Project and Feasibility
- DBetween Foundations and Deployment
How the community answered
(26 responses)- A4% (1)
- B8% (2)
- C4% (1)
- D85% (22)
Explanation
Option D is correct because in the DSDM framework, the phases flow in this order: Pre-Project → Feasibility → Foundations → Evolutionary Development → Deployment → Post-Project. Evolutionary Development is where iterative prototyping and incremental builds occur - it sits after the project's foundations are established and before the solution is deployed.
Why the distractors are wrong:
- A (Feasibility and Foundation): This gap is where Foundations itself begins, not where iterative development happens.
- B (Deployment and Post-Project): By Deployment the product is already being released; development is complete at this stage.
- C (Pre-Project and Feasibility): This is the very start of the lifecycle - nothing has been assessed yet, let alone built.
Memory tip: Think of the acronym "PFF-ED-DP" - Pre-project, Feasibility, Foundations, Evolutionary Development, Deployment, Post-project. The "ED" in the middle reminds you that Evolutionary Development is the core building phase sandwiched between setup (Foundations) and release (Deployment).